Final Project: Project Charter
Final Project: Project Charter
The project charter is one of the more important project documents. It authorizes the project, provides the purpose and justification for the project and provides the criteria to judge project success. Final Project: Project Charter
The specific parts of the St. Dismas Assisted Living Facility case study you will need to prepare the project charter are listed below.
Meredith, J.R., Shafer, S.M., Mantel, Jr., S.J., Sutton, M. (2014). Project management in practice (5th ed.). Hoboken, NJ: Wiley.
Part 1: St. Dismas Assisted Living Facility – 1 (pp. 106-108)
Part 2: St. Dismas Assisted Living Facility Project Budget Development—2 (pp. 147-148)
Part 3: St. Dismas Assisted Living Facility Program Plan—3 (pp. 193-196)
St. Dismas Assisted Living Facility Construction Project Plan (pp. 195-196)
ORDER ORIGINAL, PLAGIARISM-FREE ESSAY PAPERS HERE
Your project charter must include:
Project Description
- Purpose and Justification for the project
- Objectives of the project
- High Level Project Requirements
- Tangible Measures of Project Success
Project Assumptions and Constraints
- Assumptions for the Project
- Constraints for the Project
Project Milestone Timeline Chart
- Construction Milestone Timeline (labeled)
- Stakeholder Register
Project Approval Procedures
Refer to the Project Charter Template for specific instructions on how to develop the project charter.
References:
Meredith, J.R., Shafer, S.M., Mantel, Jr., S.J., Sutton, M. (2014). Project management in practice (5th Ed.). Hoboken, NJ: Wiley.
Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). Sixth edition. Newtown Square, PA: Author.
St. Dismas Assisted Living Facility—1
St. Dismas Medical Center, an urban, nonprofit, 450 bed rehabilitation hospital began to
see a significant decline in admissions. St. Dismas’ mission focuses on inpatient and
outpatient rehabilitation of the severely injured and catastrophically ill. While the patient
census varied from month to month, it appeared to the St. Dismas Board of Trustees that
the inpatient population was slowly but steadily declining. The hospital’s market
researchers reported that fewer people were being severely injured due to the popularity
of seat belts and bicycle/motorcycle helmets. In order to get a handle on the future of the organization, the Board, and theCEO, Fred Splient M.D. called for a major strategic
planning effort to take place.
In January 1999, St. Dismas held a planning retreat to identify future opportunities. The
outcome of the retreat was that the Medical Center needed to focus its efforts around two major strategic initiatives. The first, a short run initiative, was to be more cost
effective in the delivery of inpatient care. The second, a long-run strategy, was to develop new
programs and services that would capitalize on the existing, highly competent rehabilitation therapy staff and St. Dismas’s excellent reputation in the region.
At the time of the retreat, Fred Splient’s parents were living with him and his family. Fred
was an active member of the “sandwich generation.” His parents were aging and
developing many problems common to the geriatric populace. Their increased medical
needs were beginning to wear on Fred and his family. It crossed Fred’s mind that life
might be more pleasant if the hospital Board approved an expansion of the Medical Center’s campus to include an assisted living facility.
In March 1999, Fred had his Business Development team prepare a rough estimate of the
potential return on investment of an assisted living facility. He asked the team to identify
different options for facility construction and the associated costs. The team also did a
complete competitive analysis and examined the options for services to be offered based
on St. Dismas’s potential population base and catchment area. The Business Development
team visited several facilities across the country. The team also interviewed companies
that could oversee the design, building, and operation of the facility for St. Dismas. The
development team produced a preliminary business plan based on the recommended
structure for the facility, estimated capital expenditure needs, estimated income from
operation of the facility, as well as projected revenues to other Medical Center programs
resulting from the facility’s population.
The plan was presented at the May 1999 meeting of the Board of Trustees. Fred Splient
and his team introduced the Board to the concept of opening an assisted living facility on
St. Dismas’s campus. The facility would be set up as a for-profit subsidiary of the Medical Center so that it could generate a profit and not be subjected to the strict guidelines of the hospital’s accrediting agencies. As a subsidiary organization, however, the Board would still have control.
The chosen facility design was a freestanding apartment-
like facility with a sheltered connection to the Hospital for access to the kitchen and hospital services. The facility would have 100 units with 15 to 30 of the units classified as “heavy-
assisted” and built to code to house the physically and medically disabled. The rest of the units would be “light-assisted,” larger apartments. The population would be approximately 110 to 150
residents, with most being single occupants rather than couples.
The light-assisted apartments could hold residents who required only minor medical and
socialinterventions. The residents of the heavy-assisted section would have more medical
needs and would require assistance getting around. The Business Development team
recommended this type of programming model, because many assisted living facilities
were erected across the country, but few had a medical focus and offered the types of
services that St. Dismas could offer—physical and occupational therapy programs, and
behavior management programs to name a few.
The Board was assured that the facility would meet the strategic initiative of a growing
business. The business plan projected an immediate increase in the number of referrals to
the outpatient therapy programs. Another projected deliverable of the project was to
enable St. Dismas to strengthen its focus on reimbursable preventive and wellness
programs for the healthier geriatric population. The project’s longer term goal was to
increase the census in the hospital’s inpatient units by having a location where people
could age in place until they were in need of hospitalization, and then such a facility
would be right next door.
Depending on the exact size of the apartments, their equipment, and the actual ratio of
heavy-to light-assisted units, Fred estimated that the entire project would cost between
$8,500,000 and $11,000,000 for the facility construction. That estimate included the cost
of land, furnishings, and a sheltered connection to the hospital. When up and running, it
was estimated that the net income would range between $9,000 and $12,000 per un
it per year. The team estimated the net cash flow for the entire project to be around $1,500,000
per year.
Fred requested the Board to approve the concept and allow his team to prepare a pro
forma plan to the Board for approval. The plan would include a recommended design for
both heavy-and light-assisted apartments. It would also include all costs of land,
construction, furnishings, and staffing. Income estimates would be included and would be
conservatively biased. A timetable would also be included.
The Board conducted several executive sessions, and by the middle of May voted to
approve the concept. They approved the architectural-construction-
management firm recommended by the team, and they requested Splient to proceed with developing a complete project plan. The Board appointed two Board members to sit on Fred’s planning group. Final Project: Project Charter
In June, Dr. Splient gathered his executive team together and presented the project
mission, and scope. He reported that the board had approved a small budget to finance
the planning process. The Board also stipulated that construction could not begin until
after the November 1999 city elections because two of the Board Members were running
in that election, one for a city council seat and one as a county commissioner. The Board
also stated that they would like a plan that would allow the facility to open by July 2000,
as research has shown that many adult children find the summer the easiest time to assist
their parents in finding an alternative to independent living arrangements. The CEO and
executive team were now confident that they were ready to launch the project to plan,
build, and open an assisted living facility at St. Dismas.
A few days later, Fred decided that it was time to set up the team that would take
Responsibility for what he called the ALF project. He quickly decided to include the
following staff at the launch meeting:
Chief Financial Officer (CFO)
Vice President of Business Development and Marketing
Rehab Services Medical Director
Construction Project Manager for capital facilities projects
Chief Operations Officer (COO) (nursing, facilities, food services, and
housekeeping)
Director of Information Services
Director of Support Services (central supply, purchasing, and security)
Two members of the Board of Trustees, one with construction experience and the
other a probable electee to the city council.
Even though the department directors from Support Services and Information Services
would not be involved until later, Fred decided to include them from the beginning. Fred
knew some members of his team had a tendency to become obstacles to progress if they
felt left out.
Fred named the group the ALF Project Steering Committee and held the first meeting.
Fred presented his vision for the facility. He told the group that he personally would be
managing this project. He led a discussion of all the major steps that must be included in
the project plan, and asked each team member to identify the areas for which they would
accept responsibility. The hospital’s Construction Project Manager took responsibility for
the construction of the facility, and the COO volunteered to oversee the building design,
as well as define the needs for food services, housekeeping, staffing, and policy and
procedure development. The CFO agreed to develop the budgets for each area of the
project as well as the operating budget for the facility. The CFO also agreed to create the
payroll and accounting systems necessary to operate the facility.
The IS director accepted responsibility to define and set up all the telecommunications
and information system needs of the facility. The VP of Business Development agreed to
create a preliminary marketing plan, and a communication package for the community
and hospital staff. In addition, she discussed organizing a major ground breaking event.
The Medical Director said that he would design an assessment tool for determining
residents’ level of medical needs upon moving in to the facility. He felt this was the first
step in defining what clinical services should be offered to residents. Fred told the team
that he would develop the management structure for the new facility and work with in-
house counsel to identify all governmental regulations as well as all industry standards
that pertain to an assisted living facility and govern the facility’s practices. Splient gave
the team two months to come back with their detailed action plans for their areas of
responsibility. Final Project: Project Charter
(Project Name)
Student Name
Walden University
Date
Table of Contents
Project Assumptions and Constraints. 3
Project Milestone Timeline Chart 3
Project Description
The project description is a summary of the project and the deliverables or outcomes expected as a result of conducting the project. The project description typically includes a statement of the purpose of the project and the justification for undertaking the project from a business perspective. It also includes project objectives, high-level requirements, and how project success will be measured.
Write a project description based on Part 1 of the “St. Dismas Assisted Living Facility” case study. The project description should:
- State the purpose and justification for the project.
- Describe the objectives of the project.
- Describe the high-level requirements for the project.
- Describe the tangible measures of project success.
(3–4 paragraphs)
Project Assumptions and Constraints
Project assumptions are factors that may be true but are not confirmed and can impact the project. Constraints are factors that impose limits or boundaries on the project.
Summarize the assumptions and constraints for the project that are described in Part 1 and Part 2 of the “St. Dismas Assisted Living Facility” case study. To complete this part of the project:
- Describe the assumptions for the project.
- Describe the constraints for the project.
(2–3 paragraphs)
Project Milestone Timeline Chart
Project milestones represent significant points or events in the project lifecycle. In the project schedule Gantt chart, milestones are represented with durations of 0 and a symbol such as a diamond. For many projects, a milestone timeline chart is developed as a visual that is typically used to communicate to executive stakeholders who most likely won’t want to see the detailed schedule. Final Project: Project Charter
Refer to Part 3 of the “St. Dismas Assisted Living Facility” case study.
After much consideration, it was decided that construction of the assisted living facility (ALF) would begin on March 1, 2000. Given that, the construction of the first 45 units would be complete by May 1, 2001 and all construction would be complete by June 4, 2001. The project would be finished and the buildings ready for residents by July 30, 2001. To complete this part of the project:
- Prepare a milestone timeline chart based on Table 4, the “St. Dismas ALF Construction Project Plan,” showing the start and finish dates of the project as well as the name and finish date for each milestone in the construction project plan.
- Describe each of the project milestones in the milestone timeline chart.
Stakeholder Register
A stakeholder is any individual, group, or organization that may have influence over the direction of a project and/or may be impacted by the result of a project. The stakeholder register is created out of the “Identify Stakeholder” process. It typically includes at least the stakeholder’s name, organization they are associated with, title, role in the project, and whether or not they are internal or external stakeholders.
Create a stakeholder register based on Part 1 and Part 2 of the “St. Dismas Assisted Living Facility” case study. To complete the Stakeholder Register:
- List the names, organizations, and titles of all individuals or entities that may be involved in the project. Indicate whether each stakeholder is internal or external to the project organization and what role each will fulfill on the project.
Name | Organization | Title | Role | Internal/External |
Project Approval Procedure
The project approval procedure is a formalized process for obtaining stakeholder approval and sign-off before the project team can proceed to the next step in the project. Stakeholder approval is typically required at milestones in the project when major project deliverables are completed. Final Project: Project Charter
Using the milestone timeline chart created above, describe the approval process for the project. To complete this part of the project:
- Indicate who will approve each of the milestones in the timeline chart, and describe how the approvals will be obtained.
(1 page)